Rock Creek Sewer Separation (CSO 037)
Project Map:
Scope:
- Install new storm sewer pipes to handle stormwater during wet weather events.
- Convert the existing combined sewer system into the planned sanitary sewer system.
- Rehabilitate over 850 feet of the existing sewer that is being converted to the sanitary sewer.
- Disconnect all sanitary sewer lines from the CSO 037 outfall and connect it to the proposed new storm sewer lines.
- Replace over 3,600 feet of water mains and valves in the neighborhood streets, as well as existing lead service lines, fire hydrants scheduled for repair or replacement
|
|
|